Part one of the new hitting station project is complete. Last week the concrete pad base for the new pads was installed. Now we are just waiting on the mats and paver bricks. Both items have been orders, but are still being manufactured. 

In this pic we are laying out the tee with mason's line to make sure everything is exactly how we want it. 

Trevor was on site to make sure things were going perfectly. The contractor used my sod cutter to cut all the sod. Then his guys came in behind the cutter and removed it all. 

All formed up and ready for concrete. 

Concrete, or "Mud" as it is called by contractors, is here. 

While we wait for the rest of the other projects materials to show up my staff will be busy with other parts of the project. We still need to install the drainage and do some dirt work to get ready for the paver bricks. 