The river project is still underway and has been severely slowed down by the almost daily deluge of rain in which it is intended to help with.  Seems even Mother Nature has a sense of humor on some things.  The excavation / widen phase of the project north of the RP bridge is complete.  What is left in the areas next to CCN is to grade the slopes and install the rip / rap bank stabilization.  The rock install phase is up to the area adjacent to 15 green on our side and as you can see in the picture the contractor is working on the RP side.



Here is a look from the RP side looking north by our #15 green.  The area above the rock is to be sodded with Bahia grass (the road side stuff).



The area south of the RP bridge still has to be excavated to remove all of the accumulation of silt over time.  It's been slow going, but this drainage project should help tremendously in the long run.